Approvals

Planning Permit No:

OL - PP / NHRB / 0131 / 2023

Date of Permit:

2023-04-06

Building Permission No:

CEBA / WDCN13 / 00171 / 2023

Date of Permit:

2023-04-21

TNRERA:

TN / 29 / Building / 0197 / 2023

Dated:

2023-05-10

Project Update Images

  • 4th floor, 1st coat wall putty work is completed.
  • 1st and 3rd floor primer coat painting work is in progress.
  • 1st & 3rd floor toilet wall tile laying work is completed.
  • 2nd & 4th floor toilet wall tile laying work is 50% completed.
  • 1st & 3rd floor General flooring work is completed.
  • 2nd and 4th floor General flooring work is in progress. (50% completed) & 5th floor progress
  • External primer coat painting work is completed.
  • Terrace weathering course work is in progress. (50% completed)
  • 4th floor, 1st coat wall putty work is completed.
  • 1st and 3rd floor primer coat painting work is in progress.
  • Upto 3rd floor toilet wall tile laying work is completed.
  • 4th floor toilet wall tile laying work is 80% completed.
  • 1st, 3rd & 4th floor General flooring work is completed.
  • 2nd and 5th floor General flooring work is in progress. (50% completed)
  • Terrace weathering course work is in progress. (50% completed)
  • 4th floor, 1st coat wall putty work is completed.
  • 1st, 2nd and 3rd floor primer coat painting work is in progress.
  • Upto 4th floor toilet wall tile laying work is completed.
  • 5th floor toilet wall tile laying work is in progress.
  • 1st, 3rd & 4th floor General flooring work is completed.
  • 2nd and 5th floor General flooring work is in progress. (80% completed)
  • Terrace weathering course work is completed.
  • External drainage chamber work is in progress.
  • External wall 1st coat painting work is in progress.
  • 4th floor, 1st coat wall putty work is completed.
  • 1st, 2nd and 3rd floor primer coat painting work is in progress.
  • Upto 4th floor toilet wall tile laying work is completed.
  • 5th floor toilet wall tile laying work is in progress. (70% completed)
  • 1st, 3rd & 4th floor General flooring work is completed.
  • 2nd and 5th floor General flooring work is in progress. (80% completed)
  • External drainage chamber work is in progress. (50% completed)
  • External wall 1st coat painting work is in progress. (30% completed)
  • Compound wall pile work is in progress.