Flat No. Floor Type Area Facing Layout Availability
803 8 2BHK + 2T 998 East Not Available Available

Approvals

Planning Permit No:

C / PP / MSB / 65 (A to C) / 2021

Date of Permit:

2022-01-03

Building Permission No:

CEBA / WDCN13 / 00032 / 2022

Date of Permit:

2022-01-27

TNRERA:

TN/29/BUILDING/77/2022

Dated:

2022-03-14

Project Update Images

  • 8th floor toilet plumbing work is in progress.
  • 6th and 7th floor General flooring and toilet wall tile laying work is in progress.
  • Upto 5th floor Corridor flooring work is completed
  • 5th and 6th floor inner wall primer coat painting work is in progress.
  • External primer coat painting work is completed.
  • 7th floor General flooring and toilet wall tile laying work is in progress. (90% completed)
  • Upto 6th floor Corridor flooring work is completed
  • 6th floor inner wall primer coat painting work is in progress. (30% completed)
  • External chamber work is in progress. (45% completed)
  • External 1st coat painting work is in progress. (50% completed)
  • 7th floor General flooring and toilet wall tile laying work is in progress. (95% completed)
  • Upto 6th floor Corridor flooring work is completed
  • 6th and 7th floor inner wall primer coat painting work is in progress. (35% completed)
  • External chamber work is in progress. (60% completed)
  • External 1st coat painting work is in progress. (80% completed)
  • 7th floor General flooring and toilet wall tile laying work is in progress. (95% completed)
  • Upto 6th floor Corridor flooring work is completed
  • 6th and 7th floor inner wall primer coat painting work is in progress. (35% completed)
  • External chamber work is in progress. (60% completed)
  • External 1st coat painting work is in progress. (80% completed)
  • 8th floor General flooring and toilet wall tile laying work is in progress.
  • All floor Corridor flooring work is completed (Stilt floor Balance)
  • 7th floor inner wall primer coat painting work is in progress.
  • External chamber work is in progress. (60% completed)
  • Duct plumbing work is in progress. (70% completed)
  • Terrace floor weathering course work is in progress (60% completed)