Planning Permit No:
PPA / WDCN09/01155/2023
Date of Permit:
2023-02-18
Building Permission No:
BA/WDCN09/01185/2023
Date of Permit:
2023-02-18
Project Update Images
-
-
-
-
- Flat inner wall primer coat painting work is completed.
- All floor window grill fixing work is 90% completed.
- All floors Lobby flooring work is completed.
- Flat wood work is in progress. (Flat 2B)
- Drainage chamber work is in progress. (95% completed)
- Setback area earth filling work is in progress. (80% completed)
- Flat inner wall primer coat painting work is completed.
- All floor window grill fixing work is completed.
- All floors Lobby flooring work is completed.
- Flat wood work is in progress. (Flat 2A & 2B)
- Drainage chamber work is in progress. (95% completed)
- Setback area earth filling work is in progress. (80% completed)
- Compound wall brick work is in progress.
- Flat wood work is in progress. (Flat 2A & 2B)
- Drainage chamber work is in progress. (95% completed)
- Setback area earth filling work is in progress. (80% completed)
- Compound wall brick work is in progress. (50% completed)
- Flat wood work is in progress. (Flat 2A & 2B)
- Setback area earth filling work is in progress. (80% completed)
- Compound wall brick work is in progress. (60% completed)