Planning Permit No:
PPA / WDCN09/01155/2023
Date of Permit:
2023-02-18
Building Permission No:
BA/WDCN09/01185/2023
Date of Permit:
2023-02-18
Project Update Images
-
-
-
-
- 2nd floor plastering work is in progress. (90% completed)
- 3rd floor plastering work is in progress. (80% completed)
- 2nd and 3rd floor toilet plumbing work is in progress.
- 1st floor toilet wall tile laying work is in progress.
- Terrace parapet wall plastering work is 80% completed.
- External plastering work is in progress. (80% completed)
- 3rd floor inner plastering work is completed.
- 2nd and 3rd floor toilet plumbing work is in progress.
- 1st floor toilet wall tile laying work is in progress. (50% completed)
- Terrace parapet wall plastering work is completed.
- External plastering work is in progress. (90% completed)
- 3rd floor inner plastering work is completed.
- 3rd floor toilet plumbing work is in progress.
- 1st floor toilet wall tile laying work is in progress. (50% completed)
- 2nd floor toilet wall tile laying work is in progress. (30% completed)
- Terrace parapet wall plastering work is completed.
- External plastering work is in progress. (90% completed)
- Stilt floor beam plastering work is 50% competed.
- 3rd floor toilet plumbing work is in progress. (70% completed)
- 1st floor General flooring and toilet wall tile laying work is in progress. (50% completed)
- 2nd floor General flooring and toilet wall tile laying work is in progress. (30% completed)
- Terrace floor weathering course work is in progress.
- External plastering work is in progress. (90% completed)