- All floors – primer coat painting work is progress.
- Flat wood work is in progress. ( 8 flats)
- Lift erection work is in progress (1/2 completed)
- Compound wall work is completed.
- External paving block laying work is in progress. (40% completed)
- External Duct covering work is in progress.
- External 1st coat painting work is completed.
- Project Completion Certificate obtained.
- All service connection is obtained.
- All floors – primer coat painting work is progress.
- Flat wood work is in progress. ( 8 flats)
- Lift erection work is in progress (1/2 completed)
- Compound wall work is completed.
- External paving block laying work is in progress. (50% completed)
- External Duct covering work is completed.
- Project Completion Certificate obtained.
- All service connection is obtained.
- All floors – primer coat painting work is progress. (90% completed)
- Flat inner 1st coat painting work is in progress (10 flat completed)
- Flat wood work is in progress. ( 7 flats)
- Flat wood work is completed. ( 2/20 flats)
- Lift erection work is in progress (1/2 completed)
- Terrace floor plumbing pipe ring main work is in progress.
- External paving block laying work is in progress. (75% completed)
- Project Completion Certificate obtained.
- All service connection is obtained.
- All floors – primer coat painting work is completed.
- Flat inner 1st coat painting work is in progress (10 flat completed)
- Flat wood work is in progress. (8 flats)
- Flat wood work is completed. (2/20 flats)
- Lift erection work is in progress (1/2 completed)
- Terrace floor plumbing pipe ring main work is completed.
- External paving block laying work is completed.
- External 1st coat painting work is completed.
- Project Completion Certificate obtained.