Master Layout Plan
×
Approvals
Planning Permit No:
OL-PP/NHRB/0222/2024
Date of Permit:
2024-05-28
Building Permission No:
CEBA/WDCN10/00245/2024
Date of Permit:
2024-06-11
Project Update Images
-
-
-
-
- 3rd floor block work is completed.
- 4th floor block work is in progress. (80% completed)
- 5th floor block work is in progress. (70% completed)
- 1st floor inner plastering work is completed.
- 2nd floor inner plastering work is in progress. (80% completed)
- 1st and 2nd floor toilet plumbing concealed pipe work is in progress.
- 3rd floor block work is completed.
- 4th floor block work is in progress. (80% completed)
- 5th floor block work is in progress. (70% completed)
- 1st and 2nd floor inner plastering work is completed.
- 1st and 2nd floor toilet plumbing concealed pipe work is in progress.
- Upto 4th floor block work is completed.
- 5th floor block work is in progress. (70% completed)
- 1st and 2nd floor inner plastering work is completed.
- 3rd floor inner plastering work is in progress. (50% completed)
- 1st, 2nd and 3rd floor toilet plumbing concealed pipe work is in progress.
- Upto 4th floor block work is completed.
- 5th floor block work is in progress. (80% completed)
- Upto 3rd floor inner plastering work is completed.
- 4th floor inner plastering work is in progress. (30% completed)
- 2nd and 3rd floor toilet plumbing concealed pipe work is in progress.