Master Layout Plan
×
Approvals
Planning Permit No:
OL-PP/NHRB/0222/2024
Date of Permit:
2024-05-28
Building Permission No:
CEBA/WDCN10/00245/2024
Date of Permit:
2024-06-11
Project Update Images
-
-
-
-
- Upto 2nd floor roof concrete work is completed.
- 3rd floor column work is completed.
- 3rd floor roof shuttering work is in progress.
- Upto 3rd floor roof concrete work is completed.
- 4th floor column barbending work is in progress
- 1st floor block work is in progress.
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is completed.
- 1st floor block work is in progress. (30% completed)
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is completed.
- 4th floor roof shuttering and barbending work is in progress.
- 1st floor block work is in progress. (70% completed)
- 2nd floor block work is in progress.