Master Layout Plan
×
Approvals
Planning Permit No:
OL-PP/NHRB/0222/2024
Date of Permit:
2024-05-28
Building Permission No:
CEBA/WDCN10/00245/2024
Date of Permit:
2024-06-11
Project Update Images
-
-
-
-
- 2nd & 5th floor toilet wall tile laying work is in progress.
- 2nd & 3rd floor general flooring work is in progress. (80% completed)
- Staircase flooring work is in progress. (50% completed)
- External plastering work is in progress. (80% completed)
- 2nd & 3rd floor toilet wall tile laying work is completed.
- 5th floor toilet wall tile laying work is in progress.
- 2nd & 3rd floor general flooring work is completed.
- 5th floor general flooring work is in progress.
- Staircase flooring work is in progress. (90% completed)
- External plastering work is in progress. (90% completed)
- 2nd & 3rd floor toilet wall tile laying work is completed.
- 5th floor toilet wall tile laying work is in progress. (90% completed)
- 2nd & 3rd floor general flooring work is completed.
- 5th floor general flooring work is in progress. (90% completed)
- Elevation groove work is in progress (50% completed)
- External plastering work is in progress. (90% completed)
- 1st floor toilet wall tile laying work is in progress.
- 2nd, 3rd and 4th floor general flooring work is completed.
- 5th floor general flooring work is in progress. (90% completed)
- Elevation groove work is in progress (70% completed)
- External plastering work is completed.