Master Layout Plan
×
Approvals
Planning Permit No:
OL-PP/NHRB/0222/2024
Date of Permit:
2024-05-28
Building Permission No:
CEBA/WDCN10/00245/2024
Date of Permit:
2024-06-11
Project Update Images
-
-
-
-
- 1st floor toilet wall tile laying work is in progress.
- 2nd, 3rd and 4th floor general flooring work is completed.
- 5th floor general flooring work is in progress. (90% completed)
- Elevation groove work is in progress (70% completed)
- External plastering work is completed.
- 1st floor toilet wall tile laying work is completed.
- 1st floor general flooring work is in progress.
- 5th floor general flooring work is in progress. (90% completed)
- Lift erection work is in progress.
- Lift wall cladding work is in progress.
- Elevation groove work is in progress (90% completed)
- Terrace weathering course work is in progress.
- Lift erection work is in progress.
- Lift wall cladding work is in progress.
- Elevation groove work is in progress (90% completed)
- Terrace weathering course work is in progress.(50% completed).
- Outer chamber work is in progress.
- Lift erection work is in progress. (50% completed).
- Lift wall cladding work is in progress.
- Elevation groove work is completed.
- Terrace weathering course work is completed.
- Outer chamber work is in progress.(50% completed)
- Duct plumbing work is in progress.
- 2nd ,3rd &4th floor Inner 1st coat putty work is in progress