Amenities
Generator Backup
Elevators
Master Layout Plan
×
Approvals
Planning Permit No:
OL-PP/NHRB/0250/2024
Date of Permit:
2024-05-31
Building Permission No:
CEBA/WDCN09/00259/2024
Date of Permit:
2024-06-20
Project Update Images
-
-
-
-
- 5th floor inner plastering work is completed.
- 4th floor Toilet wall tiles work is in progress. (90% completed)
- 4th floor general flooring work is in progress.(90% completed)
- 5th floor general flooring work is in progress.(40% completed
- Duct plumbing work is in progress. (40% completed)
- External 1st coat painting work is in progress.
- 5th floor inner plastering work is completed.
- 5th floor Toilet wall tiles work is in progress. (90% completed)
- 5th floor general flooring work is in progress.(90% completed
- Duct plumbing work is in progress. (70% completed)
- External 1st coat painting work is completed
- Lift erection work is in progress.
- 5th floor inner plastering work is completed.
- 5th floor Toilet wall tiles work is completed.
- 5th floor general flooring work is completed.
- Duct plumbing work is in progress. (90% completed)
- External 1st coat painting work is completed
- Lift erection work is in progress.
- • Duct plumbing work is completed.
- • External 1st coat painting work is completed
- • Outer chamber work is in progress.
- • Lift erection work is in progress.
- • Lift wall cladding work is in progress.