Project Update Images
-
-
-
-
- All floors block work is completed.
- 1st floor inner plastering work is in progress. (90% completed)
- 2nd floor inner plastering work is in progress. (40% completed)
- Upto 3rd floor toilet plumbing work is in progress.
- 1st floor inner plastering work is in progress. (90% completed)
- 2nd floor inner plastering work is in progress. (70% completed)
- External plastering work is in progress.
- Upto 4th floor toilet plumbing work is in progress.
- 1st floor inner plastering work is in progress. (90% completed)
- 2nd floor inner plastering work is in progress. (90% completed)
- 3rd floor inner plastering work is in progress.
- External plastering work is in progress. (50% completed)
- Upto 4th floor toilet plumbing work is in progress.
- 1st & 2nd floor inner plastering work is completed.
- 3rd floor inner plastering work is in progress. (50% completed)
- 4th floor inner plastering work is in progress. (30% completed)
- External plastering work is in progress. (70% completed)
- Upto 4th floor toilet plumbing work is in progress.