Planning Permit No:
OL-PP/NHRB/0250/2024
Date of Permit:
2024-05-31
Building Permission No:
CEBA/WDCN09/00259/2024
Date of Permit:
2024-06-20
Project Update Images
-
-
-
-
- Upto 4th floor roof concrete work is completed.
- 1st floor block is in progress. (75% completed)
- 2nd floor block work is in progress (40% completed)
- Upto 4th floor roof concrete work is completed.
- 5th floor column work is completed.
- 5th floor roof shuttering work is in progress.
- 1st floor block is in progress. (75% completed)
- 2nd floor block work is in progress (60% completed)
- 3rd floor block work is in progress (30% completed)
- All floors roof concrete work is completed.
- 1st floor block is in progress. (75% completed)
- 2nd floor block work is in progress (70% completed)
- 3rd floor block work is in progress (30% completed)
- All floors roof concrete work is completed.
- 1st floor block is in progress. (75% completed)
- 2nd floor block work is in progress (70% completed)
- 3rd floor block work is in progress (70% completed)
- 4th floor block work is in progress (50% completed)