Approvals
Planning Permit No:
PPA / WDCN10/12216/2022
Date of Permit:
2022-12-31
Building Permission No:
BA/WDCN10/09021/2022
Date of Permit:
2022-12-31
Project Update Images
-
-
-
-
- Stilt floor Column and Beam plastering work is in progress. (90% completed)
- All floors Toilet plumbing work is completed.
- 2nd floor general flooring and toilet wall tiles laying work is in progress.
- Terrace weathering course work is in progress. (80% completed)
- External plastering work is in progress. (90% completed)
- Stilt floor Column and Beam plastering work is in progress. (90% completed)
- All floors Toilet plumbing work is completed.
- 1st floor general flooring and toilet wall tiles laying work is in progress. (90% completed)
- 2nd floor general flooring and toilet wall tiles laying work is in progress (80% completed)
- 3rd floor general flooring and toilet wall tiles laying work is in progress (50% completed)
- Terrace weathering course work is in progress. (80% completed)
- External plastering work is in progress. (90% completed)
- External Duct plumbing work is in progress.
- Stilt floor Column and Beam plastering work is in progress. (90% completed)
- 1st floor general flooring and toilet wall tiles laying work is completed.
- 2nd floor general flooring and toilet wall tiles laying work is in progress (90% completed)
- 3rd floor general flooring and toilet wall tiles laying work is in progress (90% completed)
- Terrace weathering course work is completed.
- External plastering work is completed.
- External Duct plumbing work is in progress.
- Stilt floor Column and Beam plastering work is in progress. (90% completed)
- 3rd floor general flooring and toilet wall tiles laying work is in progress (90% completed)
- External plastering work is completed.
- External Duct plumbing work is in progress. (50% completed)