Master Layout Plan
×
Availability
3B |
3 |
2BHK + 2T |
1080 |
South |
|
Available |
5B |
5 |
2BHK + 2T |
1080 |
South |
|
Available |
Project Update Images
-
-
-
-
- • 5th floor toilet wall tile work is in progress (75% completed)
- • 5th floor General flooring work is in progress.
- • Upto 3rd floor inner wall primer coat painting work is completed.
- • Flat wood work is in progress (Flat 1A, 2A & 3A)
- • Duct plumbing work is in progress.
- • Compound wall work is in progress.
- 5th floor toilet wall tile work is in progress (75% completed)
- 5th floor General flooring work is in progress.
- Upto 3rd floor inner wall primer coat painting work is completed.
- Flat wood work is in progress (Flat 1A, 2A & 3A)
- Duct plumbing work is in progress.
- Compound wall work is in progress.
- 5th floor toilet wall tile work is in progress (50% completed)
- 5th floor General flooring work is in progress. (50% comleted)
- Flat inner wall primer coat painting work is in progress. (Flats 8/10 completed)
- Flat wood work is in progress (Flat 1A, 2A & 3A)
- Duct plumbing work is in progress.
- Compound wall work is completed.
- 5th floor toilet wall tile work is in progress (50% completed)
- 5th floor General flooring work is in progress. (50% comleted)
- Flat inner wall primer coat painting work is in progress. (Flats 8/10 completed)
- Flat wood work is in progress (Flat 1A, 2A & 3A)
- Duct plumbing work is in progress.
- Outer chamber work is in progress (80% completed)