Project Update Images
-
-
-
-
-
- 4th floor column work is completed.
- 4th floor roof shuttering work is in progress.
- 1st & 2nd floor block work is in progress (70% completed)
- 3rd floor block work is in progress (30% completed)
- 4th floor column work is completed.
- 4th floor roof shuttering and barbending work is in progress.
- 1st floor block work is completed.
- & 2nd floor block work is in progress (75% completed)
- 3rd floor block work is in progress (30% completed)
- 4th floor column work is completed.
- 4th floor roof concrete work is completed.
- 1st & 2nd floor block work is completed.
- 3rd floor block work is in progress (70% completed)
- Upto 4th floor roof concrete work is completed.
- 5th floor roof shuttering work is in progress.
- 3rd floor block work is in progress (70% completed)
- 1st floor inner plastering work is in progress.
- All floors roof concrete work is completed.
- 3rd floor block work is completed.
- 1st floor inner plastering work is in progress. (50% completed)