Project Update Images
-
-
-
-
- 2nd floor inner plastering work is completed.
- 3rd floor inner plastering work is in progress.(50% completed)
- 4th floor brick work is completed.
- 5th floor brick work is in progress.(70% completed)
- Head room roof shuttering & barbending work is in progress.
- 2nd floor inner plastering work is completed.
- 3rd floor inner plastering work is completed.
- 4th floor brick work is completed.
- 4th Floor inner plastering work is in progress.(25% completed)
- 5th floor brick work is in progress.(70% completed)
- Head room roof concrete work is completed.
- 3rd floor inner plastering work is completed.
- 4th floor brick work is completed.
- 4th Floor inner plastering work is in progress.(50% completed)
- 5th floor brick work is in progress.(70% completed)
- Terrace parapet wall plastering work is in progress.
- Duct wall brick work is in progress
- 3rd floor inner plastering work is completed.
- 4th floor brick work is completed.
- 4th Floor inner plastering work is in progress.(60% completed)
- Toilet plumbing work is in progress.(1st,2nd And 3rd floor progress)
- 5th floor brick work is in progress.(70% completed)
- Terrace parapet wall plastering work is in progress.(60% completed)
- Duct wall brick work is in progress.(50% completed)