Project Update Images
-
-
-
-
- 4th Floor inner plastering work is completed.
- 5th floor inner plastering work is in progress.(20% completed)
- Toilet plumbing work is in progress.(1st,2nd, 3rdand 4th floor progress)
- Terrace parapet wall plastering work is in progress.(60% completed)
- External plastering work is in progress.(30% completed)
- 5th floor inner plastering work is in progress.(50% completed)
- Toilet plumbing work is in progress.(1st,2nd, 3rd,4th&5th floor progress)
- Terrace parapet wall plastering work is in progress.(60% completed)
- External plastering work is in progress.(40% completed)
- Head room tank work is in progress.(shuttering & bar bending work progress)
- 5th floor inner plastering work is completed.
- Toilet plumbing work is in progress.(1st,2nd and 3rd floor completed, 4th and 5th floor progress.)
- Terrace parapet wall plastering work is in progress.(60% completed)
- External plastering work is in progress.(50% completed)
- Head room tank work is in progress.(shuttering & bar bending work progress)
- Duct wall brick work is completed.
- 5th floor inner plastering work is completed.
- Toilet plumbing work is in progress.(1st,2nd and 3rd floor completed, 4th and 5th floor progress.)
- Terrace parapet wall plastering work is in progress.(60% completed)
- External plastering work is in progress.(70% completed)
- Head room tank work is completed.
- Duct wall brick work is completed.