Project Update Images
-
-
-
-
- 4th floor roof concrete work is completed.
- 5th floor column work is in progress
- 1st floor block work is completed.
- 2nd floor block work is in progress. (75% completed)
- 3rd floor block work is in progress. (70% completed)
- 4th floor roof concrete work is completed.
- 5th floor column work is completed
- 2nd floor block work is completed.
- 3rd floor block work is in progress. (70% completed)
- 1st floor plastering work is in progress.
- All floors roof concrete work is completed.
- 2nd floor block work is completed.
- 3rd floor block work is in progress. (70% completed)
- 1st floor plastering work is in progress.(80% completed)
- 1st floor inner plastering work is completed.
- 2nd floor inner plastering work is in progress. (30% completed)
- 3rd floor block work is in progress. (70% completed)
- 4th floor block work is in progress. (50% completed)
- 5th floor roof concrete work is completed.