Project Update Images
-
-
-
-
- 1st floor inner plastering work is completed.
- 2nd floor inner plastering work is in progress. (30% completed)
- 3rd floor block work is in progress. (70% completed)
- 4th floor block work is in progress. (50% completed)
- 5th floor roof concrete work is completed.
- 1st floor inner plastering work is completed.
- 2nd floor inner plastering work is completed.
- 3rd floor block work is in progress. (80% completed)
- 4th floor block work is in progress. (70% completed)
- 5th floor roof concrete work is completed.
- 1st floor inner plastering work is completed.
- 2nd floor inner plastering work is completed.
- 3rd floor block work is completed.
- 4th floor block work is in progress. (70% completed)
- 5th floor roof concrete work is completed.
- Head room roof shuttering work is in progress.
- 2nd floor inner plastering work is completed.
- 3rd floor inner plastering work is in progress.
- 4th floor block work is in progress. (80% completed)
- Head room roof shuttering work is in progress.