Project Update Images
-
-
-
-
- Basement brick work is completed.
- Basement earth refilling work is in progress.
- Basement PCC work is in progress.
- Stilt floor column work is completed.
- Basement PCC work is (50% completed).
- Stilt floor column work is completed.
- Basement PCC work is (50% completed).
- Stilt floor column work is completed.
- Sump work is in progress
- Stilt floor column work is completed.
- Stilt floor roof shuttering work is in progress.
- Sump work is completed.