Ocean Dew - Block IV

Pallikaranai

Enquire Now

Amenities

Gymnasium
Elevators
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Playground
Theatre

Master Layout Plan

Approvals

Planning Permit No:

C/PP/MSB/49 (A to F)/2019

Date of Permit:

2019-11-05

Building Permission No:

CEBA/WDCN14/00040/2020

Date of Permit:

2020-01-28

TNRERA:

TN/29/BUILDING/0274/2021

Dated:

2021-09-01

Project Update Images

  • General flooring and toilet tile laying work is completed
  • Lift erection work is in progress. (1/3 completed).
  • External plumbing work is in progress. (90% completed)
  • Swimming pool Rcc work is completed.
  • Rain water Trench work is completed.
  • Compound wall plastering work is completed.
  • Flat wood work is in progress. (Flat 2A)
  • External paving block laying work is in progress. (60% completed)
  • General flooring and toilet tile laying work is completed
  • Lift erection work is in progress. (2/3 completed).
  • External plumbing work is in progress. (90% completed)
  • Swimming pool work is completed.
  • Rain water Trench work is completed.
  • Compound wall plastering work is completed.
  • Flat wood work is in progress. (Flat 2A)
  • External paving block laying work is in progress. (60% completed)
  • General flooring and toilet tile laying work is completed
  • Lift erection work is in progress. (2/3 completed).
  • External plumbing work is in progress. (90% completed)
  • Swimming pool work is completed.
  • Rain water Trench work is completed.
  • Compound wall plastering work is completed.
  • Wood work is in progress. (3 Flats )
  • External paving block laying work is in progress. (60% completed)
  • General flooring and toilet tile laying work is completed
  • Lift erection work is in progress. (2/3 completed).
  • External plumbing work is completed.
  • Swimming pool work is completed.
  • Rain water Trench work is completed.
  • Compound wall plastering work is completed.
  • Wood work is in progress. (3 Flats )
  • External paving block laying work is in progress. (60% completed)