Contact Us

Ramaniyam Real Estates,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 +91 9710928855 +91 7299922617 sales@ramaniyam.com

Nagas Courtyard

Adyar

Download Brochure

Download file

Enquire Now

Amenities

Generator Backup
Multi Purpose Hall

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
1A 1 3BHK + 3T 1420 West Sold Out
2A 2 2BHK + 2T 1420 West Sold Out
3A 3 3BHK + 3T 1420 West Available
`3B 3 2BHK + 2T 1129 West Available
5B 5 2BHK + 2T 1129 West Sold Out
4A 4 3BHK + 3T 1420 West Sold Out
5A 5 3BHK + 3T 1420 West Sold Out
4B 4 2BHK + 2T 1129 West Sold Out
2B 2 2BHK + 2T 1129 West Sold Out
1B 1 2BHK + 2T 1129 West Sold Out

Approvals

Planning Permit No:

OL - PP / NHRB / 0318 / 2023

Date of Permit:

2023-08-17

Building Permission No:

CEBA / WDCN13 / 00333 / 2023

Date of Permit:

2023-09-05

TNRERA:

TN / 29 / Building / 0420 / 2023

Dated:

2023-10-11

Project Update Images

  • 4th & 5th floor inner wall plastering work is in progress.(80% completed).
  • 5th floor toilet wall concealed pipe line plumbing work is in progress.
  • Upto 3rd floor window jambs granite fixing work is in progress.
  • External plastering work is in progress. (50% completed)
  • 4th & 5th floor inner wall plastering work is completed.
  • 5th floor toilet wall concealed pipe line plumbing work is in progress.
  • Upto 3rd floor window jambs granite fixing work is completed.
  • 2nd floor toilet wall tile laying work is in progress.
  • External plastering work is in progress. (70% completed)
  • 5th floor toilet wall concealed pipe line plumbing work is in progress.
  • 2nd floor toilet wall tile laying work is in progress. (60% completed)
  • 1st floor general flooring work is in progress.
  • External plastering work is in progress. (70% completed)
  • 5th floor toilet wall concealed pipe line plumbing work is in progress. (60% completed)
  • 3rd floor toilet wall tile laying work is in progress.
  • 1st and 2nd floor general flooring work is in progress.
  • All floors window jambs granite fixing work is 50% completed.
  • External plastering work is in progress. (80% completed)

Property Location

Let your dreams be our

next Project!