- Pile Cap earth excavation work is in progress.
- Sump work is completed.
- Pile cap concrete work is in progress. (75% completed)
- Plinth beam concrete work is in progress. (75% completed)
- Pile cap concrete work is completed
- Plinth beam concrete work is completed
- Stilt floor column work is completed
- Stilt floor column work is completed
- Stilt floor roof shuttering work is in progress.
- Stilt floor column concrete work is completed
- Stilt floor roof shuttering work is in progress.