Planning Permit No:
OL-PP/NHRB/0134/2024
Date of Permit:
2024-04-03
Building Permission No:
CEBA/WDCN13/00156/2024
Date of Permit:
2024-04-15
TNRERA:
TN/29/BUILDING0367/2024
Project Update Images
-
-
-
-
- Inner 1st coat painting work is in progress. (flats – 2C,3B& 5B completed)
- Duct covering work is completed.
- External chamber work is in progress. (90% completed)
- External GSB filling work is in progress.
- Compound wall work is completed.
- Wood work –All 11 flats is in progress.
- Inner 1st coat painting work is in progress. (flats –2A, 2C,3A,3B& 5B completed)
- Duct covering work is completed.
- External chamber work is completed.
- External GSB filling work is completed.
- Landscape ledge wall brick work is in progress.
- Wood work –( 10 flats is in progress, 1 flat completed)
- Inner 1st coat painting work is in progress. (flats –2A, 2C,3A,3B ,4C &5B completed)
- Paving block work is in progress. (75% completed)
- External chamber work is completed.
- Landscape ledge wall work is completed.
- Wood work –( 8 flats is in progress, 4 flat is completed)
- Inner 1st coat painting work is in progress. (flats –2A, 2C,3A,3B ,4C &5B completed)
- Paving block work is in progress. (75% completed)
- Landscape ledge wall work is completed.
- Wood work –( 8 flats is in progress, 4 flat is completed)