Planning Permit No:
OL-PP/NHRB/0134/2024
Date of Permit:
2024-04-03
Building Permission No:
CEBA/WDCN13/00156/2024
Date of Permit:
2024-04-15
TNRERA:
TN/29/BUILDING0367/2024
Project Update Images
-
-
-
-
- 4th floor inner plastering work completed.
- 5th floor inner plastering work is in progress. (50% completed)
- 5th floor toilet concealed pipe plumbing work is in progress.
- 3rd floor toilet wall tile laying work is completed.
- External plastering work is in progress. (30% completed)
- 4th floor inner plastering work completed.
- 5th floor inner plastering work is in progress. (70% completed)
- 5th floor toilet concealed pipe plumbing work is in progress.
- 4th floor toilet wall tile laying work is in progress.
- External plastering work is in progress. (30% completed)
- 4th floor inner plastering work completed.
- 5th floor inner plastering work is in progress. (80% completed)
- 4th floor toilet wall tile laying work is in progress.
- External plastering work is in progress. (40% completed)
- 4th floor inner plastering work completed.
- 5th floor inner plastering work is in progress. (90% completed)
- 5th floor toilet wall tile laying work is in progress.
- Staircase flooring work is in progress.
- External plastering work is in progress. (40% completed)