Ashok Vihar

Ashok Nagar

Download Brochure

Download file

Enquire Now

Amenities

Generator Backup
Elevators
24/7 Power Backup
Rain Water Harvesting

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
5B 5 2BHK + 2T 1026 South Available

Approvals

Planning Permit No:

OL-PP/NHRB/C/0032/2025,

Date of Permit:

2025-02-03

Building Permission No:

CEBA / WDCN10 / 00063 / 2025

Date of Permit:

2025-02-12

TNRERA:

TN/29/Building/0159/2025

Dated:

2025-04-30

Project Update Images

  • 1st floor Inner plastering work is in progress (80% completed).
  • 2nd floor Inner plastering work is in progress (50% completed)
  • 3rd floor Inner plastering work is in progress.
  • 4th floor block work is completed.
  • 5th floor block work is in progress (70% completed).
  • Outer plastering work is in progress.(30% completed)
  • Terrace floor parapet wall plastering work is in progress.
  • Sump work is in progress.
  • 1st floor Inner plastering work is in progress (90% completed).
  • 2nd floor Inner plastering work is in progress (60% completed)
  • 3rd floor Inner plastering work is in progress. (25% completed)
  • Outer plastering work is in progress.(40% completed)
  • Terrace floor parapet wall plastering work is in progress.
  • Sump work is in progress.
  • 1st floor Inner plastering work is completed.
  • 2nd floor Inner plastering work is in progress (80% completed)
  • 3rd floor Inner plastering work is in progress. (30% completed)
  • 4th floor Inner plastering work is in progress. (30% completed)
  • Outer plastering work is in progress.(50% completed)
  • Terrace floor parapet wall plastering work is completed.
  • Sump work is completed.
  • Upto 2nd floor Inner plastering work is completed.
  • 3rd floor Inner plastering work is in progress. (50% completed)
  • 4th floor Inner plastering work is in progress. (50% completed)
  • Outer plastering work is in progress.(60% completed)