Contact Us

Ramaniyam Real Estates,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 +91 9710928855 +91 7299922617 sales@ramaniyam.com

Anugraha

Ashok Nagar

Download Brochure

Download file

Enquire Now

Amenities

Gymnasium
CCTV
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Walking Track

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
1007 10 3BHK + 2T 1313 East Available
106 1 1BHK + 1T 863 East Available
710 7 2BHK + 2T 1137 South Available

Approvals

Planning Permit No:

PP/HRB/48/2022/ A to G

Date of Permit:

2022-11-15

Building Permission No:

CEBA/WDCN10/00360/2022

Date of Permit:

2022-11-23

TNRERA:

TN/29/Building/0495/2022

Dated:

2022-12-05

Project Update Images

  • Upto 8th floor inner plastering work is completed
  • 9th floor inner plastering work is in progress. (90% completed)
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 7th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (30 Flats completed)
  • STP sump 2, work is in progress.
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 8th floor staircase flooring work is completed.
  • External plastering work is in progress. (90% completed).
  • External duct plastering work is in progress. (80% completed).
  • Upto 9th floor inner plastering work is completed
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 8th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (40 Flats completed)
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 8th floor staircase flooring work is completed.
  • External plastering work is in progress. (90% completed).
  • External duct plastering work is in progress. (90% completed).
  • Upto 9th floor inner plastering work is completed
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 8th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (43 Flats completed)
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 9th floor staircase flooring work is completed.
  • External plastering work is completed.
  • External duct plastering work is completed.
  • Upto 9th floor inner plastering work is completed
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 8th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (62 Flats completed)
  • General floor tile laying work is in progress (44 Flats completed)
  • Lift erection work is completed.
  • Upto 9th floor staircase flooring work is completed.
  • External texture painting work is in progress. (60% completed)
  • Upto 9th floor inner plastering work is completed
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 8th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (65 Flats completed)
  • General floor tile laying work is in progress (60 Flats completed)
  • Lift erection work is completed.
  • Upto 9th floor staircase flooring work is completed.
  • Compound wall work is in progress (east side )
  • External texture painting work is in progress. (60% completed)
  • Upto 9th floor inner plastering work is completed
  • Upto 10th floor toilet plumbing work is in progress.
  • Upto 9th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (75 Flats completed)
  • General floor tile laying work is in progress (70 Flats completed)
  • All floors staircase flooring work is completed.
  • Compound wall work is in progress (east side) (30% completed)
  • External texture painting work is in progress. (90% completed)

Property Location

Let your dreams be our

next Project!