Master Layout Plan
×
Approvals
Planning Permit No:
PP/HRB/48/2022/ A to G
Date of Permit:
2022-11-15
Building Permission No:
CEBA/WDCN10/00360/2022
Date of Permit:
2022-11-23
TNRERA:
TN/29/Building/0495/2022
Project Update Images
-
-
-
-
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (99 flats completed)
- Flats wood work is in progress. (50 flats)
- Trench work is completed.
- Podium area landscape civil work is in progress. (90% completed)
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (99 flats completed)
- Flats wood work is in progress. (50 flats)
- Trench work is completed.
- Podium area landscape civil work is in progress. (90% completed)
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (99 flats completed)
- Flats wood work is in progress. (52 flats)
- Elevation cladding work is in progress. (80% completed)
- Podium area landscape civil work is in progress. (90% completed)
- Project Completion Certificate obtained.
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (102 flats completed)
- Flats wood work is in progress. (52 flats)
- Elevation cladding work is in progress. (85% completed)
- Podium area landscape civil work is in progress. (90% completed)
- Project Completion Certificate obtained.