Master Layout Plan
×
Availability
106 |
1 |
1BHK + 1T |
863 |
East |
|
Available |
Approvals
Planning Permit No:
PP/HRB/48/2022/ A to G
Date of Permit:
2022-11-15
Building Permission No:
CEBA/WDCN10/00360/2022
Date of Permit:
2022-11-23
TNRERA:
TN/29/Building/0495/2022
Project Update Images
-
-
-
-
- Toilet wall tile laying work is in progress (122 Flats completed)
- General floor tile laying work is in progress (122 Flats completed)
- All floor doors fixing work is in progress. (79 flats completed)
- Flats wood work is in progress. (12 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (90% completed)
- Drainage chamber work is in progress (75% completed)
- Trench work is in progress (90% completed)
- Toilet wall tile laying work is in progress (126 Flats completed)
- General floor tile laying work is in progress (126 Flats completed)
- All floor doors fixing work is in progress. (85 flats completed)
- Flats wood work is in progress. (15 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (90% completed)
- Drainage chamber work is in progress (80% completed)
- Trench work is in progress (90% completed)
- All sides compound wall work is in progress (85% completed)
- Toilet wall tile laying work is in progress (130 Flats completed)
- General floor tile laying work is in progress (130 Flats completed)
- All floor doors fixing work is in progress. (85 flats completed)
- Flats wood work is in progress. (15 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (90% completed)
- Drainage chamber work is in progress (80% completed)
- Trench work is in progress (90% completed)
- All sides compound wall work is in progress (85% completed)
- Toilet wall tile laying work is in progress (130 Flats completed)
- General floor tile laying work is in progress (130 Flats completed)
- All floor doors fixing work is in progress. (85 flats completed)
- Flats wood work is in progress. (18 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (90% completed)
- Drainage chamber work is in progress (80% completed)
- Trench work is in progress (90% completed)
- All sides compound wall work is in progress (85% completed)