Contact Us

Ramaniyam Real Estates,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 sales@ramaniyam.com

Anugraha

Ashok Nagar

Download Brochure

Download file

Enquire Now

Amenities

Gymnasium
CCTV
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Walking Track

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
202 2 4BHK + 4T 2277 West Not Available Available
106 1 1BHK + 1T 863 East Available
710 7 2BHK + 2T 1137 South Available

Approvals

Planning Permit No:

PP/HRB/48/2022/ A to G

Date of Permit:

2022-11-15

Building Permission No:

CEBA/WDCN10/00360/2022

Date of Permit:

2022-11-23

TNRERA:

TN/29/Building/0495/2022

Dated:

2022-12-05

Project Update Images

  • 8th floor block work is in progress. (70% completed)
  • Terrace parapet wall brick work is completed.
  • 4th and 5th floor inner plastering work is in progress
  • Upto 5th floor toilet plumbing work is in progress.
  • 1st to 5th floor external plastering work is in progress.
  • 8th floor block work is in progress. (70% completed)
  • Terrace parapet wall plastering work is completed.
  • 4th and 5th floor inner plastering work is in progress
  • Upto 6th floor toilet plumbing work is in progress.
  • 1st to 5th floor external plastering work is in progress. (40% completed)
  • Terrace floor weathering course work is in progress.
  • 8th floor block work is in progress. (80% completed)
  • Terrace parapet wall plastering work is completed.
  • 4th, 5th and 6th floor inner plastering work is in progress
  • Upto 6th floor toilet plumbing work is in progress.
  • Lift wall plastering work is in progress (60% completed)
  • 1st to 5th floor external plastering work is in progress. (50% completed)
  • Terrace floor weathering course work is in progress.
  • 8th floor block work is completed.
  • 9th floor block work is in progress. (80% completed)
  • 10th floor block work is in progress. (40% completed)
  • 5th, 6th and 7th floor inner plastering work is in progress.
  • Upto 6th floor toilet plumbing work is in progress.
  • Lift wall plastering work is in progress (70% completed)
  • 1st to 5th floor external plastering work is in progress. (50% completed)
  • Terrace floor weathering course work is in progress. (40% completed)
  • 8th floor block work is completed.
  • 9th floor block work is in progress. (80% completed)
  • 10th floor block work is in progress. (40% completed)
  • 5th floor inner plastering work is in progress. (60% completed)
  • 6th and 7th floor inner plastering work is in progress. (50% completed)
  • Upto 6th floor toilet plumbing work is in progress.
  • Lift wall plastering work is in progress (70% completed)
  • 1st to 5th floor external plastering work is in progress. (60% completed)
  • Terrace floor weathering course work is in progress. (75% completed)