Master Layout Plan
×
Approvals
Planning Permit No:
PPA/WDCN13/07259/2024
Date of Permit:
2024-08-17
Building Permission No:
BA/WDCN13/05820/2024
Date of Permit:
2024-08-17
Project Update Images
-
-
-
-
- External primer work is in progress.
- Stilt floor plastering work is completed.
- Inner putty work in all floors is completed.
- Lobby flooring work is in progress.(90% completed)
- General flooring work is completed.
- Stilt floor common toilet plastering work is completed.
- External primer work is completed.
- Lobby flooring work is in progress.(90% completed)
- All floors General flooring work is completed.
- Life erection work is in progress.(60% completed)
- Duct plumbing work is in progress.
- External 1st coat painting work is in progress.
- External primer work is completed.
- Lobby flooring work is in progress.(90% completed)
- All floors General flooring work is completed.
- Life erection work is in progress.(70% completed)
- Duct plumbing work is in progress. . (40% completed)
- External 1st coat painting work is in progress .(90% completed)
- Lobby flooring work is in progress.(90% completed)
- All floors General flooring work is completed.
- Life erection work is in progress.(80% completed)
- All floor lift wall cladding work is in progress.
- Duct plumbing work is in progress. (40% completed)
- External 1st coat painting work is completed.