Amenities
Generator Backup
Elevators
Approvals
Planning Permit No:
OL - PP/NHRB/0052/2023
Date of Permit:
2023-02-10
Building Permission No:
CEBA/WDCN13/00066/2023
Date of Permit:
2023-02-24
TNRERA:
TN/29/Building/0133/2023
Project Update Images
-
-
-
-
-
- Footing concrete work is in progress (18/24 completed)
- Stub column concrete work is 18 nos completed.
- Earth refilling work is in progress.
- UG Sump RCC wall work is completed.
- Footing concrete work is in progress (18/24 completed)
- Earth refilling work is in progress.
- Plinth beam shuttering and barbending work is in progress.(Partial work)
- Footing concrete work is in progress (18/24 completed)
- Earth refilling work is in progress.
- Plinth beam concrete work is in progress.(65% completed)
- Brickwork above plinth beam is in progress.(40% completed)
- UG sump RCC wall work is completed.
- Footing concrete work is in progress (18/24 completed)
- Earth refilling work is in progress.
- Plinth beam concrete work is in progress.(65% completed)
- Brickwork above plinth beam is in progress.(40% completed)
- UG sump RCC wall work is completed.
- Footing concrete work is in progress (22/24 completed)
- Earth refilling work is in progress. (65% completed)
- Plinth beam concrete work is in progress.(65% completed)
- Brickwork above plinth beam is in progress.(65% completed)
- UG Sump Rcc wall work is completed.