Project Status+
Projects status as on 1st March 2021
Projects status as on 22nd February 2021
Projects status as on 15th February 2021
Projects status as on 8th February 2021
Projects status as on 1st February 2021
Projects status as on 25th January 2021
-
-
-
-
-
-
-
-
- All floor window grill fixing work is completed.
- Flat wood work is in progress.(5/6 flats).
- Lift erection work is in progress.
- Lift wall cladding work is completed.
- External 1st coat painting work is completed.
- External 1st coat painting work is completed.
- Plumbing duct covering work is in progress.
- Project C.C obtained.
Projects status as on 18th January 2021
Projects status as on 11th January 2021
Projects status as on 4th January 2021
Projects status as on 28th December 2020
Projects status as on 21st December 2020
Projects status as on 14th December 2020
Projects status as on 7th December 2020
Projects status as on 23rd November 2020
-
-
-
-
-
-
-
-
- 3rd floor 1st coat putty painting work is completed
- 1st floor window grill fixing work is in progress
- Lift erection work is in progress.
- Terrace ring main work is in progress.
- External plastering work is completed.
- External chamber work is in progress.
- Terrace weathering course work is completed.
- Gate fixing work is completed.
Projects status as on 16th November 2020
-
-
-
-
-
-
-
- All floor toilet wall tiles laying work is completed.
- 3rd floor general flooring work is completed.
- 3rd floor 1st coat putty painting work is completed
- 1st floor window grill fixing work is in progress
- Lift erection work is in progress.
- Terrace ring main work is in progress.
- External plastering work is completed.
Projects status as on 9th November 2020
-
-
-
-
-
-
- All floor toilet wall tiles laying work is completed.
- 3rd floor general flooring work is in progress.
- External plastering work is completed.
- 3rd floor general flooring work is in progress.
- External plastering work is completed.
- Terrace weathering course work is completed.
- Gate fixing work is in progress.