Project Status+
Projects status as on 12th April 2021
Projects status as on 5th April 2021
-
-
-
-
-
-
-
-
-
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is completed.
- 3rd floor general flooring work is completed.
- Lift erection work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External paving work is in progress.
- External primer coat painting work is completed.
Projects status as on 29th March 2021
-
-
-
-
-
-
-
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is in progress.
- 3rd floor general flooring work is in progress.
- Lift erection work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External paving work is in progress.
- External primer coat painting work is completed.
Projects status as on 22nd March 2021
-
-
-
-
-
-
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is in progress.
- 3rd floor general flooring work is in progress.
- Lift erection work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
- External primer coat painting work is completed.
Projects status as on 15th March 2021
-
-
-
-
-
-
-
-
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is in progress.
- Lift erection work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
- Compound wall work is in completed.
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B,2C & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B, 2C & 3A, 3C).
Projects status as on 8th March 2021
-
-
-
-
-
-
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is completed.
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
- Compound wall work is in completed.
Projects status as on 1st March 2021
-
-
-
-
-
-
-
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is completed.
- 1st floor general tile flooring work is completed.
- 3rd floor toilet tile laying work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
- Compound wall work is in progress.
Projects status as on 22nd February 2021
-
-
-
-
-
-
-
-
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is completed.
- 1st floor general tile flooring work is in progress.
- All floors Staircase and lobby flooring work is completed.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
- Compound wall work is in progress.
Projects status as on 15th February 2021
-
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is completed.
- All floors Staircase and lobby flooring work is completed.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 8th February 2021
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is completed.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 25th January 2021
-
-
-
-
-
-
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is in progress.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
Projects status as on 18th January 2021
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is in progress.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 11th January 2021
-
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is in progress.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 4th January 2021
Projects status as on 28th December 2020
Projects status as on 21st December 2020
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- 1st and 2nd floor – first coat putty work is completed,3rd floor progress
- 1st floor mockup flat general flooring work is completed.
- Auditorium work is in progress.
- External plastering work is in progress.
Projects status as on 14th December 2020
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- 1st and 2nd floor – first coat putty work is completed,3rd floor progress
- 1st floor mockup flat general flooring work is completed.
- Auditorium work is in progress.
- External plastering work is in progress.
Projects status as on 7th December 2020
Projects status as on 30th November 2020
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 23rd November 2020
-
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 16th November 2020
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 9th November 2020
Projects status as on 2nd November 2020
-
-
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is 90% completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 27th October 2020
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is 90% completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 19th October 2020
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 12th October 2020
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 5th October 2020
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 28th September 2020
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.