
Availability+
Floor | Flat / Section | Area (Sq. Ft.) | Availability | No of Bedrooms |
---|---|---|---|---|
Floor 1 | FLAT – 1A | 3093 | SOLD OUT | Four |
FLAT – 1B | 3093 | AVAILABLE | Four | |
Floor 2 | FLAT – 2A | 3093 | AVAILABLE | Four |
FLAT – 2B | 3093 | AVAILABLE | Four | |
Floor 3 | FLAT – 3A | 3093 | SOLD OUT | Four |
FLAT – 3B | 3093 | SOLD OUT | Four | |
Floor 4 | FLAT – 4A | 5695 | SOLD OUT | Four |
Project Status+
Projects status as on 18th January 2021
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is in progress.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 11th January 2021
-
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- Upto 3rd floor – first coat putty work is completed.
- All floors UPVC window fixing work is in progress.
- All floors Staircase and lobby flooring work is in progress.
- Auditorium work is in progress.
- External chamber work is in progress.
- External plastering work is completed.
Projects status as on 4th January 2021
Projects status as on 28th December 2020
Projects status as on 21st December 2020
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- 1st and 2nd floor – first coat putty work is completed,3rd floor progress
- 1st floor mockup flat general flooring work is completed.
- Auditorium work is in progress.
- External plastering work is in progress.
Projects status as on 14th December 2020
-
-
-
-
-
-
-
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is completed.
- 1st and 2nd floor – first coat putty work is completed,3rd floor progress
- 1st floor mockup flat general flooring work is completed.
- Auditorium work is in progress.
- External plastering work is in progress.
Projects status as on 7th December 2020
Projects status as on 30th November 2020
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 23rd November 2020
-
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 16th November 2020
-
-
-
-
-
-
- Upto 3rd floor block work is completed.
- Upto 3rd floor inner wall plastering work is completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st and 2nd floor 1st coat putty work is in progress
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 9th November 2020
Projects status as on 2nd November 2020
-
-
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is 90% completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- 1st floor toilet and general flooring work is in progress.
- External plastering work is in progress.
Projects status as on 27th October 2020
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is 90% completed.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 19th October 2020
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 12th October 2020
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 5th October 2020
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 28th September 2020
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 21st September 2020
-
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 14th September 2020
-
-
-
-
-
-
-
-
- 4th floor column concrete work is 50% competed.
- 4TH floor roof concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- Upto 3rd floor toilet concealed plumbing pipe line work is in progress.
- External plastering work is in progress.
Projects status as on 7th September 2020
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed.
- 4TH floor roof shuttering and barbending work is in progress.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- 2nd floor toilet concealed plumbing pipe line work is in progress.
Projects status as on 31st August 2020
-
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed.
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- 2nd floor toilet concealed plumbing pipe line work is in progress.
Projects status as on 17th August 2020
-
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed
- Upto 3rd floor block work is completed.
- Upto 2nd floor inner wall plastering work is completed.
- 3rd floor inner wall plastering work is in progress.
- 2nd floor toilet concealed plumbing pipe line work is in progress.
Projects status as on 17th August 2020
-
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed.
- Upto 2nd floor block work is completed.
- 3rd floor block work is 90% completed.
- 1st floor inner wall plastering work is completed.
- 2nd floor inner wall plastering work is completed.
- 2nd floor toilet concealed plumbing pipe line work is in progress.
Projects status as on 3rd August 2020
-
-
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed.
- Upto 2nd floor block work is completed.
- 3rd floor block work is in progress
- 1st floor inner wall plastering work is completed.
- 2nd floor inner wall plastering work is in progress.
- 1st floor toilet concealed plumbing pipe line work is completed.
Projects status as on 27th July 2020
-
-
-
-
-
-
- Upto 3rd floor roof concrete work is completed.
- 4th floor column concrete work is 50% competed.
- Upto 2nd floor block work is completed.
- 3rd floor block work is in progress
- 1st floor inner wall plastering work is completed.
- 2nd floor inner wall plastering work is in progress.
- 1st floor toilet concealed plumbing pipe line work is completed.