Project Status+
Projects status as on 7th December 2020
Projects status as on 30th November 2020
Projects status as on 23rd November 2020
Projects status as on 16th November 2020
Projects status as on 2nd November 2020
Projects status as on 27th October 2020
Projects status as on 19th October 2020
Projects status as on 12th October 2020
Projects status as on 5th October 2020
Projects status as on 28th September 2020
Projects status as on 21st September 2020
Projects status as on 14th September 2020
Projects status as on 7th September 2020
Projects status as on 31st August 2020
-
-
-
-
-
-
- Flats final coat painting work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 24th August 2020
-
-
-
-
-
-
- Flats final coat painting work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 17th August 2020
-
-
-
-
-
-
- Flats final coat painting work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 10th August 2020
-
-
-
-
-
-
-
- Flats final coat painting work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 3rd August 2020
-
-
-
-
-
- Flats final coat painting work is completed.(1A & 1B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 27th July 2020
-
-
-
-
-
-
- Flats final coat painting work is completed.(1A & 1B)
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External final coat painting work is completed.
- C.C obtained
- All service connection is obtained.
Projects status as on 13th July 2020
-
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External 1st coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 7th July 2020
-
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A,1B & 2A,2B)
- Flat wood work is in progress. (Flat 3A & 3B progress)
- 1st & 2nd floor toilet CP and Sanitary fitting fixing work is completed.
- External 1st coat painting work is completed.
- C.C obtained.
- All service connection is obtained.
Projects status as on 15th June 2020
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A,1B & 2A)
- Flat wood work is in progress. (Flat 2B, 3A & 3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- All service connection is obtained
Projects status as on 9th June 2020
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B, 2A &2B, 3A & 3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- All service connection is obtained
Projects status as on 1st June 2020
-
-
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B, 2A &2B, 3A & 3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- EB connection obtained.
- Metro and drainage connection obtained
Projects status as on 25th May 2020
-
-
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B, 2A &2B, 3A & 3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- EB connection obtained.
- Metro and drainage connection obtained
Projects status as on 18th May 2020
-
-
-
-
-
-
-
- All floor 1st coat painting work is completed.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B, 2A &2B, 3A & 3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C obtained.
- EB connection obtained.
- Metro and drainage connection obtained
Projects status as on 16th March 2020
-
-
-
-
-
-
- All floor primer coats painting work is completed.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B,2A&2B,3A&3B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- EB connection obtained.
Projects status as on 9th March 2020
Projects status as on 2nd March 2020
-
-
-
-
-
-
-
- All floor primer coats painting work is in progress.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B,2A&2B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- EB connection obtained.
- Metro and drainage connection obtained
Projects status as on 24th February 2020
-
-
-
-
-
-
-
-
- All floor primer coats painting work is in progress.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B,2A&2B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- C.C obtained.
- EB connection obtained.
- Metro and drainage connection obtained
Projects status as on 17th February 2020
-
-
-
-
-
-
- All floor primer coats painting work is in progress.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B,2A&2B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- EB connection obtained.
- Metro and drainage connection obtained
Government Approvals+
Planning permit No : B /spl.bldg /27 / 2019, dated – 01-03-2019.
Building permit No : CEBA / WDCN09 / 00076 / 2019, dated – 08-04-2019.
TNRERA No : TN / 29 / Building / 0091 / 2019, dated – 28-06-2019.
CC NO :CC.No.EC / Central-II / 004 / 2020, dated – 09-01-2020.
Construction Specifications+
CONSTRUCTION SPECIFICATIONS
The flat is to be constructed to this specification subject to minor changes in dimension, locations found desirable or necessary to ensure sound engineering practice at the sole discretion of the Builder.
1. TYPE OF CONSTRUCTION
- RCC framed structure with non-load bearing porotherm and cement mortar walls.
- Ceiling height will be 10’ approximately except in the toilet where it will be 9’3”.
- Generally, internal partition walls will be 4 inches and outer walls will be 6 inches.
2. WALL FINISH
- Walls will generally be plastered and painted inside and outside.
- In the toilets, walls will be covered with ceramic tiles up to 7 feet in height.
- In the wash area, ceramic tiles will be provided up to a height of parapet.
- Ceramic tiles will be plain series.
3. FLOORING
- Flooring will be 3 x 3 VITRIFIED TILES for living and dining and for other areas.
- Bathroom tiles will be of 16 x16 ceramic tiles of Bonzar or equivalent reputed make of builder’s choice.
4. DOORS
- Main door will be first quality teak wood frame with paneled solid wooden door finished with varnish.
- Other doors will be with first quality country wood frames with paneled solid wooden door finished with paint.
- All door fittings will be of Dorma or equivalent.
- Main door will be provided with a lock, one aldrop, tower bolt, safety chain and peephole (Dorma make).
- Doors to the bedrooms will be provided with Dorma locks.
5. WINDOWS AND VENTILATORS
- Prefabricated windows of Fenesta / Aluminium will be provided.
- Ventilators will be of first quality wooden frames with glass louvers.
- Provision for split air conditioner will be provided in all the bedrooms
6. KITCHEN
- G 20 Black Granite slab will be provided for the kitchen cooking platform.
- A Single bowl stainless steel sink with drainboard will be provided
7. PLUMBING AND SANITARY FITTINGS
- Plumbing lines from the overhead tank to each floor.
- All closets and washbasins will be Parryware make in white colour.
- Provision in plumbing for connecting one geyser in each toilet.
- Hot and cold mixtures for the shower in each bathroom.
- Toilet closets will be floor/wall mounted EWC/IWC as desired by the Owners.
- Bathroom fittings – Jaguar CP fittings.
- Health faucets will be provided in each toilet.
8. WATER SUPPLY
- One common borewell and sump will be provided.
- Two pumps, one for borewell and one for metro water will be provided.
- Overhead tank with adequate capacity will be provided.
9. ELECTRICAL
- Concealed copper wiring with ISI branded cables and modular switches will be provided.
- Separate meter will be provided for lighting in common areas, the lift and the pumps/motors.
- Three-phase power supply with automatic phase change over switches will be provided in each flat.
- 15 Amp power plug sockets will be provided for water heater in the toilet, for air conditioners in the bedrooms, one in the kitchen and one in the service balcony for washing machine.
- In all the flats 3 Nos., 5 AMP sockets will be provided in the kitchen.
- Two 5 amp plug sockets will be provided in each bedroom. In the living room, an additional multiple socket with 3 outlets will be provided.
- One calling bell point will be provided.
- Except for the light points in the staircase and one light point in each bedroom, all other light and fan points will be controlled from a single point.
10. OTHERS
- One common name board and letterboxes for each flat will be provided at the entrance to the building.
- Concealed PVC pipes for TV antenna will be provided in the living room and bedrooms.
- A common board will be provided near the entrance to the building for the incoming telephone line, with provision for concealed wiring from this board to one in the living room and each one in the bedrooms and study rooms.
- The common area within the compound shall be paved and suitably landscaped.
- Auto door Konelift will be provided.
- A generator of adequate capacity to take care of the common amenities like motor, lift and all other 5 amp point inside the flat will be provided.
- Rainwater harvesting will be carried out in the proposed building.
- Landscaping will be provided as detailed by the project architect.
Building Specifications+
Layout Details+
Property Features+
Property Details+
FLat Area: 1,805 sq.ft
Bedrooms: 3
Bathrooms: 3
Property Map +
-
- All floor primer coats painting work is in progress.
- Flat wood work is completed. (Flat 1A)
- Flat wood work is in progress. (Flat 1B,2A&2B progress)
- Lift erection work is completed.
- External paving work is completed.
- External 1st coat painting work is completed
- EB connection obtained.
- Metro and drainage connection obtained