Floor | Flat/Section | Carpet Area | Area (Sq.ft) | Availability |
---|---|---|---|---|
Floor 1 | 1A | 1257 | 1750 | SOLD OUT |
Floor 1 | 1B | 1230 | 1750 | SOLD OUT |
Floor 1 | 1C | 1280 | 1750 | SOLD OUT |
Floor 2 | 2A | 1257 | 1750 | SOLD OUT |
Floor 2 | 2B | 1230 | 1750 | SOLD OUT |
Floor 2 | 2C | 1280 | 1750 | SOLD OUT |
Floor 3 | 3A | 1257 | 1750 | SOLD OUT |
Floor 3 | 3B | 1257 | 1750 | SOLD OUT |
Floor 3 | 3C | 1280 | 1750 | SOLD OUT |
Floor 4 | 4A | 1257 | 1750 | SOLD OUT |
Floor 4 | 4B | 1230 | 1750 | SOLD OUT |
Floor 4 | 4C | 329 | 448 | SOLD OUT |
Projects status as on 1st March 2021
Projects status as on 22nd February 2021
Projects status as on 15th February 2021
Projects status as on 8th February 2021
Projects status as on 1st February 2021
Projects status as on 25th January 2021
Projects status as on 18th January 2021
Projects status as on 11th January 2021
Projects status as on 4th January 2021
Projects status as on 28th December 2020
Projects status as on 21st December 2020
Projects status as on 14th December 2020
Projects status as on 7th December 2020
Projects status as on 30th November 2020
Projects status as on 23rd November 2020
-
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B & 3A, 3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 2B &3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 16th November 2020
-
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B & 3A, 3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 9th November 2020
-
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B & 3A, 3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 2nd November 2020
-
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B & 3A, 3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 27th October 2020
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 1A,1B,2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A, 1B, 2A, 2B & 3A, 3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 19th October 2020
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A,1B,2B &3A,3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 12th October 2020
-
-
-
-
-
-
-
- Flats final coat painting work is completed.(Flat 2A, 2B & 3A, 3C)
- Flat wood work is Completed (Flat 1A,1B,2B &3A,3C).
- Flat wood work is in progress (Flat 2C).
- Flat handed over is in progress. (Flat 3C)
- Flat handed over is in progress. (Flat 3C)
- External final coat painting work is 80% completed.
- Project C.C obtained.
- E.B and Drainage connection is obtained.
Projects status as on 5th October 2020
Projects status as on 28th September 2020
Projects status as on 21st September 2020
Projects status as on 14th September 2020
Projects status as on 7th September 2020
Projects status as on 31st August 2020
Projects status as on 24th August 2020
Projects status as on 17th August 2020
Projects status as on 10th August 2020
Projects status as on 3rd August 2020
Projects status as on 27th July 2020
Projects status as on 20th July 2020
Projects status as on 13th July 2020
-
-
-
-
-
-
-
- All floors 1st coat painting work is completed.
- Flat wood work is in progress (Flat 2B, 3A & 3C).
- All floors door fixing work is completed.
- Staircase handrail fixing work is completed.
- Lift erection work is in progress.
- External chamber brick work is completed.
- External paving block work is completed.
Projects status as on 7th July 2020
-
-
-
-
-
-
- Flat wood work is in progress (Flat 2B, 3A & 3C).
- All floors door fixing work is completed.
- Staircase handrail fixing work is completed.
- Lift erection work is in progress.
- External chamber brick work is completed.
- External paving block work is completed.
• All floors 1st coat painting work is completed.
Projects status as on 15th June 2020
Projects status as on 9th June 2020
-
-
-
-
-
-
- All floors 1st coat painting work is completed.
- Flat wood work is in progress (Flat 2B & 3C)
- All floors door fixing work is completed.
- Balcony handrail fixing work is completed.(Glass fixing balance)
- Staircase handrail fixing work is in progress.
- External chamber brick work is completed.
- External paving block work is completed
Projects status as on 1st June 2020
-
-
-
-
-
-
-
-
-
- All floors 1st coat painting work is completed.
- Flat wood work is in progress (Flat 2B & 3C)
- Terrace floor weathering course tile work is completed
- External 1st coat painting work is completed.
- All floors door fixing work is completed.
- Balcony handrail fixing work is completed.(Glass fixing balance)
- External chamber brick work is completed.
- External paving block work is in progress.
Projects status as on 25th May 2020
Projects status as on 18th May 2020
Projects status as on 16th March 2020
-
-
-
-
-
-
-
-
- All floor primer coat painting work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- Upto 3rd floor general flooring work is completed.
- Terrace floor weathering course tile work is completed
- External 1st coat painting work is completed.
- All floor door fixing work is in progress.
- Balcony handrail fixing work is in progress.
- External chamber brick work is in progress
Projects status as on 9th March 2020
-
-
-
-
-
-
-
- All floor primer coat painting work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- Upto 3rd floor general flooring work is completed.
- Terrace floor weathering course tile work is completed
- External 1st coat painting work is completed.
- All floor door fixing work is in progress.
- Balcony handrail fixing work is in progress.
- External chamber brick work is in progress
Projects status as on 2nd March 2020
-
-
-
-
-
-
-
- All floor primer coat painting work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- Upto 3rd floor general flooring work is completed.
- Terrace floor weathering course tile work is completed
- External 1st coat painting work is completed.
- All floor door fixing work is in progress.
- Balcony handrail fixing work is in progress.
- External chamber brick work is in progress
Projects status as on 24th February 2020
-
-
-
-
-
-
-
-
- 1st and 2nd floor Second coat wall putty work is completed and 3rd floor work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- Upto 3rd floor general flooring work is completed.
- Terrace floor weathering course tile work is completed
- External 1st coat painting work is completed.
- All floor door fixing work is in progress.
Projects status as on 17th February 2020
-
-
-
-
- All floor inner plastering work is completed.
- 1st and 2nd floor Second coat wall putty work is completed and 3rd floor work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- All floor general flooring work is in progress.
- External plastering work is completed.
- Terrace floor weathering course tile work is in progress
- External 1st coat painting work is completed.
Projects status as on 10th February 2020
-
-
-
-
-
-
-
- All floor inner plastering work is completed.
- 1st and 2nd floor Second coat wall putty work is completed and 3rd floor work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- All floor general flooring work is in progress.
- External plastering work is completed.
- Terrace floor weathering course tile work is in progress
- External 1st coat painting work is completed.
Planning permit No : B / Spl.Bldg / 29/ A & B / 2019, dated – 05-03-2019
Building permit No : CEBA / WDCN13 / 00142 / 2019, dated – 04-07-2019.
TNRERA No :TN/29/Building/0008/2020 dated 08.01.2020
CC.No. : C.C.No.EC / South-I /108 / 2020, dated – 16-07-2020.
CONSTRUCTION SPECIFICATIONS
1.0 TYPE OF CONSTRUCTION
1.1 RCC framed structure with non load bearing POROTHERM / BRICK masonry walls.
1.2 Ceiling height will be 11 feet approximately, except in the toilet where it will be 10 feet.
1.3 Generally internal partition walls will be 4 inches and outer walls will be 6 inches.
2.0 WALL FINISH
2.1 Walls will generally be plastered and painted inside and outside.
2.2 In the toilets, walls will be covered with ceramic tiles upto 7 feet.
2.3 In the wash area, tiles will be provided up to the height of 2 feet.
2.4 Ceramic tiles will be designer series as per builder’s Architect choice.
3.0 FLOORING
3.1 Flooring will be of vitrified tiles 2’ x 2’ for the entire flat.
3.2 Bathroom and balcony flooring tiles will be of anti-skid Tiles
4.0 DOORS
4.1 Main door frame will be of good quality wood with panelled solid wooden door finished with varnish.
4.2 Other doors will be with good quality wood frames and flush doors finished with paint.
4.3 All door fittings will be Dorma make.
4.4 Main door will be provided with Dorma lock, one aldrop, tower bolt, safety chain and peep hole.
4.5 Doors to the bedrooms will be provided with Dorma locks.
5.0 WINDOWS AND VENTILATORS
5.1 Pre fabricated windows of Fenesta make will be provided.
5.2 Pre fabricated windows of Fenesta make will be provided.
5.3 Split A/c provision will be provided in all bedrooms.
6.0 KITCHEN
6.1 G 20 Black Granite slab will be provided for the kitchen cooking platform.
6.2 A Single bowl stainless steel sink with drain board will be provided
7.0 PLUMBING AND SANITARY FITTINGS
7.1 Concealed plumbing lines from the overhead tank for each floor.
7.2 All closets and wash basins will be of white colour (Parryware).
7.3 Provision in plumbing for connecting one geyser in each toilet.
7.4 Hot and cold mixers for shower and tap in each toilet.
7.5 Toilet closets will be floor / wall mounted EWC / IWC as desired by the owners.
7.6 Bathroom fittings – Jaguar continentals / equivalent.
7.7 Health faucets will be provided in each toilet.
8.0 WATER SUPPLY
8.1 One common bore well and metro water sump will be provided.
8.2 Two pumps one for bore and one for sump will be provided.
8.3 Common overhead tank with separate water lines for each floor will be provided.
9.0 ELECTRICAL
9.1 Concealed copper wiring with Anchor / equivalent and MK or equivalent switches will be provided.
9.2 Separate meter will be provided for lighting in common areas, the lift and the pumps / motors.
9.3 Three phase power supply with automatic phase change over switches will be provided in each flat.
9.4 15 Amp power plug sockets will be provided for water heater in the toilet, for air conditioners in the bedrooms, two in the kitchen and one in the service balcony for washing machine.
9.5 In all the flats, 5 Nos., 5 AMP sockets will be provided in the kitchen.
9.6 Two 5 amp plug sockets will be provided in each bed room. In the living room an additional multiple socket with 3 outlets will be provided.
9.7 One calling bell point will be provided.
9.8 Light points in the staircase and light and fan points on the bed side in bedrooms will be controlled from single point.
9.9 Generator with sufficient capacity for lift, pumps and lights in common areas and all light and fan points & refrigerators inside the flats will be provided.
10.0 OTHERS
10.1 One common name board and letter boxes for each flat will be provided at the entrance to the building.
10.2 Concealed PVC pipes for TV antenna will be provided in the living room and bed rooms.
10.3 A common board will be provided near the entrance to the building for incoming telephone line, with provision for concealed wiring from this board to one in the living room and each one in the bed rooms and study rooms.
10.4 The common area within the compound shall be paved and suitably landscaped
10.5 One auto door lift of reputed make (KONE) will be provided .
10.6 Rainwater harvesting will be carried out in the proposed building.
Amenities
- Elevators
- Power Backup
- Rainwater Harvesting
-
- All floor inner plastering work is completed.
- 1st and 2nd floor Second coat wall putty work is completed and 3rd floor work is in progress.
- Up to 3rd floor toilet wall tile laying work is completed and 4th floor work is in progress.
- All floor general flooring work is in progress.
- External plastering work is completed.
- Terrace floor weathering course tile work is in progress
- External 1st coat painting work is completed.