        "date": "13th October, 2026",
        "images": [
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image1-1791867287-2132934592.jpeg",
                "caption": "Toilet plumbing work is in progress.(1st & 2nd floor progress)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image2-1791867287-1282702563.jpeg",
                "caption": "4th floor plastering work is in progress. (30% completed)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image3-1791867287-845676025.jpeg",
                "caption": "6th floor block work is completed."
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image4-1791867287-611881089.jpeg",
                "caption": "7th floor block work is in progress.(70% completed)"
            }
        ]
    },
    {
        "date": "6th October, 2026",
        "images": [
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image1-1791260004-840088736.jpeg",
                "caption": "Head room column concrete work is completed"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image2-1791260004-1538410104.jpeg",
                "caption": "3rd floor plastering work is completed"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image3-1791260004-942931507.jpeg",
                "caption": "8th floor block work is in progress."
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image4-1791260004-1695111390.jpeg",
                "caption": "Toilet plumbing work is in progress.(1st & 2nd floor progress)"
            }
        ]
    },
    {
        "date": "29th September, 2026",
        "images": [
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image1-1790662556-847485884.jpeg",
                "caption": "5th floor block work is completed."
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image2-1790662556-1331979710.jpeg",
                "caption": "6th floor block work is in progress. (70% completed)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image3-1790662556-1662114858.jpeg",
                "caption": "3rd floor plastering work is in progress.(50% completed)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image4-1790662556-923704515.jpeg",
                "caption": "All floor roof concrete work is completed."
            }
        ]
    },
    {
        "date": "22nd September, 2026",
        "images": [
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image1-1790053204-824853486.jpeg",
                "caption": "All floor roof concrete work is completed."
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image2-1790053204-675690323.jpeg",
                "caption": "5th floor block work is in progress. (90% completed)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image3-1790053204-811832651.jpeg",
                "caption": "4th floor plastering work is in progress.(Electrical wall chasing work is completed)"
            },
            {
                "src": "assets\/uploads\/project-images\/Add-construct-image4-1790053204-858512609.jpeg",
                "caption": "2nd floor plastering work is completed."
            }
        ]
    }
]