Contact Us

Ramaniyam Real Estates,

14/67, 3rd Main Rd,

Gandhi Nagar, Adyar

Chennai 600 020

+91 4443447500 +91 9710928855 +91 7299922617 sales@ramaniyam.com

Purna Krishna

K.K.Nagar

Download Brochure

Download file

Enquire Now

Amenities

Generator Backup
CCTV
Elevators
Lobby
Rain Water Harvesting

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
4A 4 3BHK + 3T 1513 North Available
2A 2 3BHK + 3T 1513 North Available
5A 5 3BHK + 3T 1513 North Sold Out
2B 2 2BHK + 2T 1263 East Available
2C 2 3BHK + 3T 1693 South Available
3A 3 3BHK + 3T 1513 North Available
3B 3 2BHK + 2T 1263 East Available
3C 3 3BHK + 3T 1693 South Available
4B 4 2BHK + 2T 1263 East Available
4C 4 3BHK + 3T 1693 South Available
5B 5 2BHK + 2T 1263 East Sold Out
5C 5 3BHK + 3T 1693 South Sold Out

Approvals

Planning Permit No:

OL - PP / NHRD / 0514 / 2024, Permit No. OL – 01149

Date of Permit:

2024-08-28

Building Permission No:

CEBA / WDCN10 / 00442 / 2024

Date of Permit:

2024-09-05

TNRERA:

TN / 29 / Building / 0572 / 2024

Dated:

2024-12-10

Project Update Images

  • Pile concrete work is completed.
  • Pile cap earth excavation work is in progress.
  • Pile cap Pcc work is in progress (26/32 completed).
  • Pile cap & Plinth beam concrete work is in progress. (50% completed)
  • Basement brick work is in progress. (50% completed).
  • Pile concrete work is completed.
  • Pile cap earth excavation work is in progress.
  • Pile cap Pcc work is in progress (26/32 completed).
  • Pile cap & Plinth beam concrete work is in progress. (70% completed)
  • Basement brick work is in progress. (70% completed).
  • Stilt floor column concrete work is in progress (32/41 completed).
  • Pile cap Pcc work is completed.
  • Pile cap & Plinth beam concrete work is completed.
  • Basement brick work is in progress. (80% completed).
  • Stilt floor column concrete work is in progress (40/41 completed).
  • Pile cap Pcc work is completed.
  • Pile cap & Plinth beam concrete work is completed.
  • Basement brick work is completed.
  • Stilt floor column concrete work is completed.