Padhuka

Mylapore

Download Brochure

Download file

Enquire Now

Amenities

Generator Backup
CCTV
Elevators
Rain Water Harvesting

Master Layout Plan

Approvals

Planning Permit No:

OL - PP / NHRB / 0070 / 2023

Date of Permit:

2023-02-27

Building Permission No:

CEBA / WDCN09 / 00104 / 2023

Date of Permit:

2023-03-17

TNRERA:

TN / 29 / Building / 0162 / 2023

Dated:

2023-04-13

Project Update Images

  • 3rd floor door fixing work is completed.
  • Flat 1st coat painting work is in progress (Flat 4B)
  • External final coat painting work is in progress. (80 % completed)
  • Flat wood work is in progress (Flat – 1A, 2B, 3A & 3B)
  • External paving block laying work is in progress. (40% completed)
  • 4th floor door fixing work is in progress.
  • Flat 1st coat painting work is in progress (Flat 1A & 2B)
  • External final coat painting work is in progress. (80 % completed)
  • Flat wood work is in progress (Flat – 1A, 2B, 3A, 3B & 4B)
  • Flat wood work is completed (Flat – 1A, 2B)
  • External paving block laying work is in progress. (80% completed)
  • 4th floor door fixing work is completed.
  • Flat 1st coat painting work is in progress (Flat 1A & 2B)
  • External final coat painting work is in progress. (90 % completed)
  • Flat wood work is in progress (Flat – 1B,3A, 3B & 4B)
  • Flat wood work is completed (Flat – 1A, 2B)
  • External paving block laying work is completed)
  • Flat 1st coat painting work is in progress (Flat 1A,2B & 3A)
  • External final coat painting work is in progress. (90 % completed)
  • Flat wood work is in progress (Flat – 1B,2A& 4B)
  • Flat wood work is completed (Flat – 1A, 2B,3A&3B)
  • External paving block laying work is completed
  • Flat 1st coat painting work is in progress (Flat 1A,2B)
  • External final coat painting work is in progress. (90 % completed)
  • Flat wood work is in progress (Flat – 1B, 2A & 4B)
  • Flat wood work is completed (Flat – 1A, 2B, 3A & 3B)
  • External paving block laying work is completed
  • Project Completion Certificate obtained.