Project Update Images
-
-
-
-
- Toilet wall tile laying work is in progress (134 Flats completed)
- General floor tile laying work is in progress (134 Flats completed)
- All floor doors fixing work is in progress. (93 flats completed)
- Flats wood work is in progress. (26 flats)
- Duct plumbing work is in progress. (95% completed)
- Drainage chamber work is in progress (90% completed)
- Trench work is in progress (9% completed)
- Podium area landscape civil work is in progress.
- All sides compound wall work is completed.
- Toilet wall tile laying work is in progress (137 Flats completed)
- General floor tile laying work is in progress (137 Flats completed)
- All floor doors fixing work is in progress. (96 flats completed)
- Flats wood work is in progress. (28 flats)
- Duct plumbing work is in progress. (95% completed)
- Drainage chamber work is in progress (90% completed)
- Trench work is in progress (95% completed)
- Podium area landscape civil work is in progress.
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (99 flats completed)
- Flats wood work is in progress. (30 flats)
- Duct plumbing work is in progress. (95% completed)
- Drainage chamber work is in progress (90% completed)
- Trench work is in progress (95% completed)
- Podium area landscape civil work is in progress.
- Toilet wall tile laying work is in progress (140 Flats completed)
- General floor tile laying work is in progress (140 Flats completed)
- All floor doors fixing work is in progress. (99 flats completed)
- Flats wood work is in progress. (30 flats)
- Trench work is completed.
- Podium area landscape civil work is in progress.