Anugraha

Ashok Nagar

Download Brochure

Download file

Enquire Now

Amenities

Gymnasium
CCTV
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Walking Track

Master Layout Plan

Availability

Flat No. Floor Type Area Facing Layout Availability
1007 10 3BHK + 2T 1313 East Available
106 1 1BHK + 1T 863 East Available
710 7 2BHK + 2T 1137 South Available

Approvals

Planning Permit No:

PP/HRB/48/2022/ A to G

Date of Permit:

2022-11-15

Building Permission No:

CEBA/WDCN10/00360/2022

Date of Permit:

2022-11-23

TNRERA:

TN/29/Building/0495/2022

Dated:

2022-12-05

Project Update Images

  • Model Flat
  • Upto 8th floor inner plastering work is completed
  • 9th floor inner plastering work is in progress. (25% completed)
  • Upto 8th floor toilet plumbing work is in progress.
  • Upto 5th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (52 Flats completed)
  • General floor tile laying work is in progress (13 Flats completed)
  • STP sump 1, work is completed.
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 7th floor staircase flooring work is completed.
  • External plastering work is in progress. (80% completed).
  • External duct plastering work is in progress. (50% completed).
  • Model flat work is completed. (Flat 710)
  • Upto 8th floor inner plastering work is completed
  • 9th floor inner plastering work is in progress. (80% completed)
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 7th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (20 Flats completed)
  • STP sump 1, work is completed.
  • Upto 8th floor inner plastering work is completed
  • 9th floor inner plastering work is in progress. (90% completed)
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 7th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (25 Flats completed)
  • STP sump 2, work is in progress.
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 7th floor staircase flooring work is completed.
  • Upto 8th floor inner plastering work is completed
  • 9th floor inner plastering work is in progress. (90% completed)
  • Upto 9th floor toilet plumbing work is in progress.
  • Upto 7th floor Corridor flooring work is completed.
  • Toilet wall tile laying work is in progress (60 Flats completed)
  • General floor tile laying work is in progress (30 Flats completed)
  • STP sump 2, work is in progress.
  • Lift erection work is in progress. (3/4 completed & 1 progress)
  • Upto 8th floor staircase flooring work is completed.
  • External plastering work is in progress. (90% completed).
  • External duct plastering work is in progress. (80% completed).