Anugraha

Ashok Nagar

Download Brochure

Download file

Enquire Now

Amenities

Gymnasium
CCTV
24/7 Power Backup
Lobby
Multi Purpose Hall
Rain Water Harvesting
Walking Track

Master Layout Plan

Approvals

Planning Permit No:

PP/HRB/48/2022/ A to G

Date of Permit:

2022-11-15

Building Permission No:

CEBA/WDCN10/00360/2022

Date of Permit:

2022-11-23

TNRERA:

TN/29/Building/0495/2022

Dated:

2022-12-05

Project Update Images

  • Toilet wall tile laying work is in progress (134 Flats completed)
  • General floor tile laying work is in progress (134 Flats completed)
  • All floor doors fixing work is in progress. (93 flats completed)
  • Flats wood work is in progress. (26 flats)
  • Duct plumbing work is in progress. (95% completed)
  • Drainage chamber work is in progress (90% completed)
  • Trench work is in progress (9% completed)
  • Podium area landscape civil work is in progress.
  • All sides compound wall work is completed.
  • Toilet wall tile laying work is in progress (137 Flats completed)
  • General floor tile laying work is in progress (137 Flats completed)
  • All floor doors fixing work is in progress. (96 flats completed)
  • Flats wood work is in progress. (28 flats)
  • Duct plumbing work is in progress. (95% completed)
  • Drainage chamber work is in progress (90% completed)
  • Trench work is in progress (95% completed)
  • Podium area landscape civil work is in progress.
  • Toilet wall tile laying work is in progress (140 Flats completed)
  • General floor tile laying work is in progress (140 Flats completed)
  • All floor doors fixing work is in progress. (99 flats completed)
  • Flats wood work is in progress. (30 flats)
  • Duct plumbing work is in progress. (95% completed)
  • Drainage chamber work is in progress (90% completed)
  • Trench work is in progress (95% completed)
  • Podium area landscape civil work is in progress.
  • Toilet wall tile laying work is in progress (140 Flats completed)
  • General floor tile laying work is in progress (140 Flats completed)
  • All floor doors fixing work is in progress. (99 flats completed)
  • Flats wood work is in progress. (30 flats)
  • Trench work is completed.
  • Podium area landscape civil work is in progress.