Project Update Images
-
-
-
-
- Toilet wall tile laying work is in progress (103 Flats completed)
- General floor tile laying work is in progress (103 Flats completed)
- All floor doors fixing work is in progress. (60 flats completed)
- Flats wood work is in progress. (10 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (50% completed)
- All sides compound wall work is in progress (75% completed)
- Toilet wall tile laying work is in progress (105 Flats completed)
- General floor tile laying work is in progress (105 Flats completed)
- All floor doors fixing work is in progress. (63 flats completed)
- Upto 3rd floor balcony grill fixing work is completed.
- Flats wood work is in progress. (10 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (60% completed)
- All sides compound wall work is in progress (80% completed)
- Toilet wall tile laying work is in progress (110 Flats completed)
- General floor tile laying work is in progress (111 Flats completed)
- All floor doors fixing work is in progress. (75 flats completed)
- Upto 3rd floor balcony grill fixing work is completed.
- Flats wood work is in progress. (12 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (80% completed)
- Outer chamber work is in progress (40% completed)
- Trench work is in progress (75% completed)
- All sides compound wall work is in progress (80% completed)
- Toilet wall tile laying work is in progress (120 Flats completed)
- General floor tile laying work is in progress (120 Flats completed)
- All floor doors fixing work is in progress. (77 flats completed)
- Flats wood work is in progress. (12 flats)
- Firefighting work is in progress. (90% completed).
- Duct plumbing work is in progress. (90% completed)
- Drainage chamber work is in progress (70% completed)
- Trench work is in progress (90% completed)
- All sides compound wall work is in progress (85% completed)