click to enable zoom
Loading Maps
We didn't find any results
open map
My Location Fullscreen Prev Next
Advanced Search
We found 0 results. Do you want to load the results now ?
Advanced Search
we found 0 results

Your search results

Ramaniyam Jaganath

Plot No 7, Sivaswamy Avenue, ,
Available
SITE CUM GROUND FLOOR PLANFIRST FLOOR PLAN

.

Floor Plans

Availability

Floor Flat / Section Area (Sq. Ft.) Availability No of Bedrooms
GROUND VILLA A  1668  SOLD OUT  Triple
FIRST VILLA B 1769  AVAILABLE  Triple

Project Status

Project Status as on 11th Feb 2019

  • All floor putty work is completed.
  • All floor tile laying work is completed.
  • External plastering work is completed.
  • Terrace floor plumbing ring main system work is completed
  • Compound wall work is in progress

Project Status as on 4th Feb 2019

  • All floor putty work is completed.
  • All floor tile laying work is completed.
  • External plastering work is completed.
  • Terrace floor plumbing ring main system work is in progress
  • Compound wall work is in progress

Project Status as on 28th Jan 2019

  • All floor putty work is completed.
  • All floor tile laying work is completed.
  • External plastering work is completed.
  • Terrace floor weathering course work is completed
  • Compound wall work is in progress

Project Status as on 21st Jan 2019

  • 1st floor tile work is in progress.
  • External plastering work is completed.
  • Window grill fixing work is in progress.
  • Terrace floor weathering course work is in progress

Project Status as on 7th Jan 2019

  • All floor inner wall plastering work is completed.
  • Ground floor tile laying work is completed.
  • 1st floor tile work is in progress.
  • External plastering work is completed.
  • Window grill fixing work is in progress.
  • Terrace floor weathering course work is in progress

Project Status as on 24th Dec 2018

  • 1st floor inner wall plastering work is completed.
  • Ground floor toilet wall tile laying work is completed.
  • 1st floor toilet plumbing work is completed.
  • External plastering work is in progress.
  • OHT water proofing work is in progress

Project Status as on 17th Dec 2018

  • OHT work is completed
  • 1st floor inner wall plastering work is completed.
  • Ground floor toilet wall tile laying work is completed.
  • 1st floor toilet plumbing work is in progress.
  • External plastering work is in progress

Project Status as on 10th Dec 2018

  • OHT work is completed
  • Ground & 1st floor brick work is completed.
  • 1st floor inner wall plastering work is completed.
  • Ground floor toilet wall tile laying work is in progress.
  • 1st floor toilet plumbing work is in progress.
  • External plastering work is in progress

Construction Specifications

CONSTRUCTION SPECIFICATIONS

Property Lot Size: 2,046 ft2
Bedrooms:
Unit Size: 1796
Floors: 2
No. Of Units: 2
Rainwater Harvesting
Elevators
Power Backup

Enquire Now

Compare properties

Similar Listings

Available

Ramaniyam Guruprasad

1,177 ft2 upwards
Spacious and well ventilated apartments in Adyar.
Spacious and well ventilated apartments in Adyar. ...
Adyar
Available

Kamarajar Avenue

2,180 ft2 upwards
Spacious and well ventilated apartments with amenities aplenty.
Spacious and well ventilated apartments with amenities aplenty. ...
Adyar
Available

Ramaniyam Benco

Comfortable enclosures with well planned amenities on the IT corridor.
Comfortable enclosures with well planned amenities on the IT corridor. ...
Besant Nagar