BALA VIMALAM

5 First Street Venkateshwara Nagar , ,
Download PDF
Available

.

Availability

Floor Flat / Section Area (Sq. Ft.) Availability No of Bedrooms
Floor 1  FLAT 1A  1212 SOLD OUT  Triple
 FLAT 1B  1467 AVAILABLE  Triple
Floor 2  FLAT 2A  1212 SOLD OUT  Triple
 FLAT 2B  1467 SOLD OUT  Triple
Floor 3  FLAT 3A  1212 SOLD OUT  Triple
 FLAT 3B  1467 SOLD OUT  Triple

Construction Specifications

CONSTRUCTION  SPECIFICATIONS

Project Status

Project Status as on 17th February 2018

  • 1st floor plastering work is completed.
  • 1st floor putty work is completed.
  • 3rd floor plastering work is completed.
  • Kitchen platform work is in progress.
  • 1st floor toilet wall tile laying work is in progress.
  • 1st floor general flooring work is in progress.
  • External plastering work is completed.
  • Terrace weathering course work is in progress.
  • External primer coat painting work is in progress

Project Status as on 10th February 2018

  • 1st floor plastering work is completed.
  • 1st floor putty work is completed.
  • 2nd floor plastering work is in progress.
  • Kitchen platform work is in progress.
  • 1st floor toilet wall tile laying work is in progress.
  • External plastering work is completed.(90%)
  • External primer coat painting work is in progress

Project Status as on 3rd February 2018

  • All floor brick work is completed.
  • 1st floor plastering work is completed.
  • 1st floor putty work is in progress.
  • 2nd floor plastering work is in progress.
  • Kitchen platform work is in progress

Project Status as on 24th January 2018

  • All floor brick work is completed.
  • 1st floor plastering work is completed.
  • 1st floor toilet plumbing work is in progress.
  • 2nd floor plastering work is in progress.
  • External west side plastering work is in progress

Project Status as on 12th January 2018

  • All floor brick work is completed.
  • 1st floor plastering work is completed.
  • 1st floor toilet plumbing work is in progress.
  • 2nd floor plastering work is in progress.

Project Status as on 06th January 2018

  • OHT work is completed.
  • All floor brick work is completed.
  • 1st floor plastering work is completed.
  • 2nd floor plastering work is in progress.
  • Terrace parapet wall (inner) plastering work is completed.

Project Status as on 23rd December 2017

  • All floor roof concrete work is completed.
  • OHT work is in progress.
  • Upto 2nd floor brick work is completed.
  • 3rd floor brick work above lintel is in progress.
  • 1st floor plastering is in progress.
  • Terrace parapet wall (inner) plastering work is completed

Project Status as on 16th December 2017

  • All floor roof concrete work is completed.
  • OHT work is in progress.
  • Upto 2nd floor brick work is 90% completed.
  • 3rd floor brick work is in progress.
  • 1st floor electrical wall chasing work is completed.
  • Terrace parapet wall (inner) plastering work is completed.

Project Status as on 9th December 2017

  • 3rd floor concrete work is completed.
  • Stilt floor ceiling plastering work is in progress(50%) completed.
  • 1st & 2nd floor brick work is completed.
  • Head room roof and column work is in progress.
  • 3rd floor brick work is in progress.
  • Terrace parapet wall plastering work is in progress

Project Status as on 02nd December 2017

  • 3rd floor concrete work is completed.
  • Stilt floor ceiling plastering work is in progress(50%) completed.
  • 1st floor brick work is completed.
  • Head room roof and column work is in progress.
  • 2nd floor& 3rd floor brick work is in progress.

Project Status as on 25th November 2017

  • Upto3rd floor concrete work is completed.
  • Stilt floor ceiling plastering work is in progress.
  • 1st floor brick work is completed upto 7’ level.
  • 1st floor lintel, loft and sunshade work is completed.
  • 2nd floor& 3rdfloor  brickwork is in progress

Project Status as on 18th November 2017

  • Upto3rd floor concrete work is completed.
  • Stilt floor ceiling plastering work is in progress.
  • 1st floor brick work is completed upto 7’ level.
  • 1st floor lintel, loft and sunshade work is in progress.
  • 2nd floor brick work is in progress

Project Status as on 10th November 2017

  • Upto3rd floor concrete work is completed.
  • 1st floor brick work is in progress.
  • Stilt floor ceiling plastering work is in progress

Project Status as on 6th November 2017

  • Upto3rd floor concrete work is completed.
  • 1st floor brick work is in progress.
  • Stilt floor ceiling plastering work is in progress

Project Status as on 28th October 2017

  • Upto3rd floor concrete work is completed.
  • 1st floor brick work is in progress.
  • Stilt floor ceiling plastering work is in progress

Rainwater Harvesting
Elevators
Power Backup

Enquire Now

Compare properties

Similar Listings

Available

Thiruveragam

Spacious and well ventilated apartments with amenities aplenty.
Spacious and well ventilated apartments with amenities aplenty. ...
Teynampet
Available

Magnum

Exclusive residential apartments which will embrace your fine living.
Exclusive residential apartments which will embrace your fine living. ...
Tharamani
Available

Mugalivakkam

Spacious and well ventilated apartments in Mugalivakkam.
Spacious and well ventilated apartments in Mugalivakkam. ...
Mugalivakkam