Aparajita

Kasthuribai Nagar 2nd Main Road, ,
Download PDF
Available

..

Floor Plans

Availability

Block 1

Floor Flat / Section Area (Sq. Ft.) SOLD OUT No of Bedrooms
Floor 1  1A  1985  SOLD OUT  Triple
Floor 2  2A  1985  SOLD OUT  Triple
Floor 3  3A  1985  SOLD OUT  Triple

Project Status

Project Status as on 17th February 2018

  • Final stage finishing work is in progress.
  • Compound wall painting work is in progress.
  • All door painting work is in progress.
  • 3rd floor flat wood work is in progress.
  • All toilet sanitary fitting fixing work is in progress

Project Status as on 10th February 2018

  • 2nd coat putty work is in progress.
  • Compound wall painting work is in progress
  • All door painting work is in progress.
  • 3rd floor flat wood work is in progress.
  • All toilet sanitary fitting fixing work is in progress.

Project Status as on 3rd February 2018

  • 2nd coat putty work is in progress.
  • Lift erection work is completed.
  • Compound wall & Gate work is completed.
  • Chamber work is completed.

Project Status as on 24th January 2018

  • 2nd coat putty work is in progress.
  • Door shutter fixing work is in progress.
  • Lift erection work is completed.
  • External 1st coat painting work is completed.
  • Compound wall & Gate work is completed.
  • Chamber work is completed.
  • Car park flooring work is in progress.

Project Status as on 12th January 2018

  • 2nd coat putty work is in progress.
  • Door shutter fixing work is in progress.
  • Lift erection work is completed.
  • External 1st coat painting work is completed.
  • Compound wall & Gate work is completed.
  • Chamber work is completed.

Project Status as on 06th January 2018

  • 2nd coat putty work is in progress.
  • Door shutter fixing work is in progress.
  • Lift erection work is in progress.
  • Lift wall cladding work is in progress.
  • External 1st coat painting work is completed.
  • Compound wall & Gate work is completed.
  • Chamber work is in progress.

Project Status as on 23rd December 2017

  • All floor plastering work is completed.
  • External plastering work is completed
  • All floor 1st coat putty work is completed.
  • 2nd and 3rd floor toilet wall tile laying work is in progress.
  • 3rd floor general tile laying work is in progress.
  • Staircase flooring work is 90% completed.
  • UPVC window fixing work is completed.
  • External primer coat painting work is in progress.
  • Compound wall work is in progress

Project Status as on 16th December 2017

  • Stilt floor Column & beam plastering work is in progress.
  • All floor plastering work is completed.
  • External plastering work is 90% completed
  • All floor 1st coat putty work is completed.
  • 2nd and 3rd floor toilet wall tile laying work is in progress.
  • 3rd floor general tile laying work is in progress.
  • Staircase flooring work is 90% completed.
  • UPVC window fixing work is in progress.
  • Terrace floor water proofing work is in progress.
  • External primer coat painting work is in progress.

Project Status as on 9th December 2017

  • All floor brick work is completed.
  • 2ndfloor inner wall plastering work is completed.
  • 3rd floor electrical wall chasing work is completed (Alteration work).
  • 3rd floor brick and wall plastering work is completed (Alteration work).
  • Head room brick and ceiling plastering work is completed.
  • All floor wall putty 1stcoatis in progress.
  • External plastering all side is in progress.

Project Status as on 02nd December 2017

  • All floor brick work is completed.
  • 2ndfloor inner wall plastering work is completed.
  • 3rd floor electrical wall chasing work is completed (Alteration work).
  • 3rd floor brick and wall plastering work is completed (Alteration work).
  • Head room brick and ceiling plastering work is completed.
  • All floor wall putty 1st coat is in progress.
  • External plastering all side is in progress.

Project Status as on 25th November 2017

  • All floor brick work is completed.
  • 2ndfloor inner wall plastering work is completed.
  • 3rd floor electrical wall chasing work is in progress (Alteration work).
  • 3rd floor brick and wall plastering work is in progress (Alteration work).
  • Head room brick and ceiling plastering work is completed.
  • All floor wall putty 1stcoatis in progress.
  • 1st and 2nd floor toilet plumbing concealed pipe line work is completed

Project Status as on 18th November 2017

  • All floor brick work is completed.
  • 2nd floor inner wall plastering work is completed.
  • 3rd floor door frame fixing work is completed.
  • External plastering work is in progress.
  • 1st floor wall putty work is in progress.
  • 1st and 2nd floor toilet plumbing concealed pipe line work is completed

Project Status as on 10th November 2017

  • All floor roof concrete work is completed.
  • All floor brick work is completed.
  • 3rd floor ceiling plastering work is completed.
  • 1st floor inner wall plastering work is completed.
  • 2ndfloor inner wall plastering work is in progress

Project Status as on 6th November 2017

  • All floor roof concrete work is completed.
  • 1st floor brick work is completed.
  • 2nd and 3rdfloor above lintel level brick work is in progress.
  • 3rd floor ceiling plastering work is in progress.
  • 1st floor inner wall plastering work is in progress

Project Status as on 28th October 2017

  • All floor roof concrete work is completed.
  • 1st floor brick work is completed.
  • 2nd and 3rdupto lintel level brick work is completed.
  • Terrace parapet wall brick work is completed

Project Status as on 21st October 2017

  • All floor roof concrete work is completed.
  • 1st floor brick work is 90% completed.
  • 2nd and 3rd upto lintel level brick work is in progress.
  • Terrace parapet wall brick work is in progress

P

Construction Specifications

CONSTRUCTION  SPECIFICATIONS

 

Bedrooms:
No. Of Units: 6
Rainwater Harvesting
Elevators
Power Backup

Enquire Now

Compare properties

Similar Listings

Available

Thiruveragam

Spacious and well ventilated apartments with amenities aplenty.
Spacious and well ventilated apartments with amenities aplenty. ...
Teynampet
Available

Magnum

Exclusive residential apartments which will embrace your fine living.
Exclusive residential apartments which will embrace your fine living. ...
Tharamani
Available

Mugalivakkam

Spacious and well ventilated apartments in Mugalivakkam.
Spacious and well ventilated apartments in Mugalivakkam. ...
Mugalivakkam